Registration of Information, Education, and Communication (IEC) Activities
All clients are advised to talk to the Client Service Section (CSS) staff or the Information Officer of the Geospatial Information Service Division (GISD) to determine schedule of requested activity, documentary requirements, and processing time.

Processing time will only commence after submission of a Request Letter by the client and the External Client Request (ECR) form is accomplished by the CSS staff or GISD Information Officer. After processing of request, present AR on the day of the activity.

IEC Activities included are tour of facilities, IEC campaigns, and Map and Technology exhibits.

  CLIENT STEP AGENCY ACTION FEE TIME RESPONSIBLE PERSONNEL  
  Send Request Letter Assign Office of Primary Responsibility (OPR) None Processing time starts after client submits all requirements, if any, and CSU Staff accomplishes the ECR. Administrator
    Contact client CSU Staff
  Inquire about free printed and/or digital data and products in the request letter Discuss product specification, service requirements, availability, processing time, payment options, price, and delivery mode
01 Submit all required documents Verify all required documents None 20 min CSS Staff (GISD)
02 Wait approval of request Route ECR for approval of the conduct of IEC activity None 15 min CSS Staff (GISD)
    Approve ECR None 2 days Administrator
    Issue AR and CS forms None 5 min CSS Staff
  TOTAL PROCESSING TIME: 2 days & 40 min
  Accomplish CS form Accept and verify CS formR None Optional CSS Staff
Building a geospatially-empowered Philippines
© National Mapping and Resource Information Authority 2021
Top Page